GATE (TF) Textile 2004 Question Paper Solution | GATE/2004/TF/62

Question 62 (Textile Engineering & Fibre Science)

A twin delivery draw frame delivers slivers of count 0.14s Ne at 300 m/min with a production efficiency of 95%. The production rate in kg/hr is

(A)60
(B)120
(C)145
(D)290
[Show Answer]

Option C

No.of delivery=2

Deliver sliver count=0.14s Ne

D/F speed=300m/min

Production efficiency=95%

The production rate(kg/hr)=?

Formula-

Production rate=(No. of delivery x draw frame speed x efficiency x 0.59)/(Ne x 1000)

Production rate=(2 x 300 x 0.95 x 0.59)/(0.14 x 1000)

Production rate=144.12 kg/hr