GATE (GA) Textile 2016 Question Paper Solution | GATE/2016/GA/06

Question 06 (General Aptitude)

The following graph represents the installed capacity for cement production (in tonnes) and the actual production (in tonnes) of nine cement plants of a cement company. Capacity utilization of a plant is defined as ratio of actual production of cement to installed capacity. A plant with installed capacity of at least 200 tonnes is called a large plant and a plant with lesser capacity is called a small plant. The difference between total production of large plants and small plants, in tonnes is __120:120__.

Gate Textile Solution 2016
[Show Answer]

Write Here

Sum of large plants productions=160+190+230+190=770
Sum of small plants productions=150+160+120+100+120=650
Difference=770-650=120 (Ans)